Case Studies

Temporary Shoring Wall
A three-story, 77,000 square-foot medical office building was planned for construction in St. Louis County, Missouri. The east area of the construction site sloped upward...
Q Street Bridge Void Fill
Severe flooding of the Elkhorn River in Douglas County, Nebraska occurred during the spring of 2019 causing significant washouts at the Q Street bridge overpass. The high...
Four-Story Stair Tower
A stair tower addition to an existing four-story building experienced settlement not long after construction. The stair tower is approximately 53 feet high, 16 feet long and...
Farm Credit Services of America
A four-story office building was planned directly west of and across the road from the existing Farm Credit Service of America (FCSA) building in Omaha, NE. The new building...
Grain Silo Slab Leveling
The slab of a 60-foot diameter grain silo had experienced about 12 inches of differential settlement. The settlement caused the interior grain delivery augers and floor sweep...
St. Charles High School Building Addition
A building addition east of the St. Charles High School was designed to have concrete drilled shaft foundations near the existing building and shallow spread footings away...
Papa John's Cardinal Stadium Expansion
Papa John’s Cardinal Stadium is an open-air football stadium which is home to the University of Louisville Cardinals. A $63 million expansion project was approved for...
Shaare Emeth Renovation
Renovation plans for the existing facility included the removal and relocation of an existing interior column. The new column location would be only a few feet from the existing...
Strip Mall Renovation
The “Villages of Twin Oaks” development project was planned southeast of the Big Bend Road and Missouri State Route 141 interchange. The new development would...
Duplex Slab Support in Oxford, IA
A ranch style, slab-on-grade duplex had a stable exterior foundation but poor slab support conditions on the interior. The worst slab settlement was measured at 2 ¾...
Northwest Park Sidewalk Lifting - Davenport, IA
The sidewalk surrounding the public restroom building at Northwest Park in Davenport, Iowa experienced differential settlement, evident by faulted slab sections at some of...
STEAM Elementary School
The STEAM (Science, Technology, Engineering, Art and Math) Elementary School building, originally built in 1967, was planned to receive upgrades and renovations. This work...
Total Case Studies: 184