A four-story office building was planned directly west of and across the road from the existing Farm Credit Service of...
1-866-375-9990
A four-story office building was planned directly west of and across the road from the existing Farm Credit Service of...
The slab of a 60-foot diameter grain silo had experienced about 12 inches of differential settlement. The settlement caused the...
Severe flooding of the Elkhorn River in Douglas County, Nebraska occurred during the spring of 2019 causing significant washouts at...
A stair tower addition to an existing four-story building experienced settlement not long after construction. The stair tower is approximately...
A 31,000-square-foot nursery school and daycare addition was planned for the Southwest Bible Church located in Beaverton, Oregon. The addition...
A 12,000 square foot mezzanine addition was planned inside the existing Menards home improvement store in La Crosse, Wisconsin. Foundations...
A 53,600 square-foot structure, for the manufacture of metal roofing and siding, was planned for construction in St. Peters, Missouri....
An above-grade, 16-inch diameter, steel pipeline, used for treated water transport, was severely corroded along an approximate 910-foot long section....
A three-story, 77,000 square-foot medical office building was planned for construction in St. Louis County, Missouri. The east area of...
Located in the Wisconsin Northwoods, the Chequamegon-Nicolet National Forest covers more than 1.5 million acres of forest preserve across five...
The Wapato pump station is used to control the water level of Wapato lake, which is in the Wapato National...
A 279,000 square-foot industrial building, constructed in 2013, exhibited significant wall and floor slab settlement, with more than 12 inches...