Duplex Slab Support in Oxford, IA
A ranch style, slab-on-grade duplex had a stable exterior foundation but poor slab support conditions on the interior. The worst slab settlement was measured at 2 ¾...
Northwest Park Sidewalk Lifting - Davenport, IA
The sidewalk surrounding the public restroom building at Northwest Park in Davenport, Iowa experienced differential settlement, evident by faulted slab sections at some of...
STEAM Elementary School
The STEAM (Science, Technology, Engineering, Art and Math) Elementary School building, originally built in 1967, was planned to receive upgrades and renovations. This work...
The Engineers Club of St. Louis
The building footprint included a wedge-shaped auditorium with a lower stage and stair-stepped seating. The stage and the lower seating areas were generally constructed as...
Crane and Furnace Equipment Foundations - Aurora, Illinois
Additions planned for an existing manufacturing facility included a large furnace and a 30-ton crane. Each addition would require its own foundation system, separate from...
Billboard Foundation Stabilization - St. Charles, MO
An area of land near a major interstate was under development with multiple buildings being constructed. The construction would also include a proposed retaining wall between...
Hickey Elementary School Elevator Addition - St. Louis, MO
The Hickey Elementary School building was constructed in 1965. An elevator addition was planned for the school to comply with ADA requirements. The soil profile at the propose...
Warehouse Construction - Red Bud - Illinois
A local automotive parts distributor planned to have a new 113,000-square foot distribution warehouse built. The proposed metal building would include 20 structural column...
Washington University Parking Garage - St. Louis, MO
The parking garage was supported on drilled shaft foundations. The stonework façade was supported independently from the parking structure on shallow spread footings....
Menard Hall Renovation - Springfield, IL
Menard Hall on the Lincoln Land Community College campus is a two-story structure with offices, classrooms, and student dining. Renovations to the building included the repair...
Raintree School - St. Louis, MO
A 5,200 square-foot, two-story addition was proposed for the existing 6,800 square-foot school building. The continuous footing and three column pad locations along the east...
Hospital Renovation - Mount Vernon, IL
A second level was planned for an existing one-story building. It was determined the second story addition would overload four existing column locations. Therefore, new columns...
Total Case Studies: 189